Frequently Asked Questions
This list of FAQs is designed to answer questions that applicants may have about New York State Aid for Library Construction. If you
have questions after reviewing these FAQs, please contact Frank Rees.
|
Application Process and Criteria
- Who is eligible to apply for State Aid for Library Construction?
- How does a library go about submitting an application for a State Aid for Library Construction?
- If a library/library system received construction aid funding in the past, is it eligible to apply again under the 2018-2021 State Aid for Library Construction?
- If a library system has more than one member library interested in applying for similar projects, e.g., installing solar panels and using the same contractor, can the system batch all the projects into one application?
- Can a library/library system submit more than one project application if it has several construction projects going on in the same building?
- If a library or library system has a main library and several branches, can the library or library system apply for construction aid for more than one of the buildings in the same year?
- If the library system headquarters building is also the system’s central library, may the system apply as both a system and a member library?
- What is the application deadline?
- How does the project approval process work?
Program Specifications
- If a construction project is already completed, can the library/library system apply for funding retroactively?
- If a project has already begun but is not completed at the time of application, can the library/library system apply for funding for the cost of all work already completed prior to the filing of the application?
- Is there a minimum/maximum allocation amount?
- What kinds of projects are eligible for funding under the State Aid for Library Construction?
- Can a library buy computers and equipment and incorporate new technologies as part of a construction project?
- Can State Aid for Library Construction funds be used for Broadband infrastructure projects?
- If a library participates in a coordinated project with a Library System to provide broadband services to its own building and additional library buildings is the library allowed to apply for an individual project for their building?
- Will a project that consists of building maintenance be eligible for funding under State Aid for Library Construction?
- Are project management costs eligible for funding?
- Are architectural and engineering plans eligible for funding?
- In addition to routine maintenance, are there any other costs ineligible for funding under the State Aid for Library Construction?
- What are the matching fund requirements?
- Can State and Municipal Facilities Program (SAMS) money be used as match funds for a construction project?
- What documents are required if the project involves bonding?
- How soon after an allocation is made must a library or library system begin construction?
- How much time does a library/library system have to finish the construction project?
- Will an estimate provided by an architectural, engineering firm, or construction consulting firm be adequate for cost estimation?
- What is the payment schedule for aid?
- Does the library receiving construction aid have to file additional paperwork to get the second payment of 40%?
- What if there is a change in a project activity or vendor?
Formula Aid Breakdown
- How is construction aid funding distributed throughout the state?
- What happens to construction aid funds that are not allocated to libraries or systems within a particular library system as determined by the formula distribution?
Building Code and Other Requirements
- Are libraries required to comply with public building codes relating to the Americans with Disabilities Act (ADA)?
- Are libraries required to pay prevailing wages for projects funded through the State Aid for Library Construction?
- What is SHPO? What libraries must meet SHPO requirements?
- What is the State Education Department's Office of Facilities Planning? What libraries must meet Office of Facilities Planning requirements?
- What is the State Environmental Quality Review Act (SEQRA)? What libraries must meet SEQRA requirements?
- Does a library/library system need to provide a copy of the “Certificate of Occupancy” if applicable?
Application Process and Criteria
Q: Who is eligible to apply for State Aid for Library Construction?
A: Any public library or public library system chartered by the Regents of the State of New York or established by an act of the New York State Legislature is eligible to apply for State Aid for Library Construction.
Q: How does a library go about submitting an application for State Aid for Library Construction?
A: A library should submit an application through its public library system. Each year, the State Library publicizes the availability of state aid for public library construction, and posts application forms and other pertinent documents on its website. Interested applicants should follow the procedures outlined on the website and submit completed applications with other required documents to their public library system. After a review and evaluation of the materials, the system will forward the application to the State Library for further review and consideration.
Q: If a library/library system received construction aid funding in the past, is it eligible to apply again under the 2018-2021 State Aid for Library Construction?
A: Yes. A library/library system can submit a project application for funding in 2018-2021 even if a previously funded project remains open.
Please note, a library/library system can not receive funding for the same project more than once. The project for which funding is being requested in 2018-2021 must be different from any project(s) funded previously.
Q: If a library system has more than one member library interested in applying for similar projects, e.g., installing solar panels and using the same contractor, can the system batch all the projects into one application?
A: No. Each library must submit an individual project application for each building. However, for the purpose of achieving the best contract terms, a single contractor can be used for multiple buildings but the costs for each building must be listed separately on the quote/bid document.
Q: Can a library/library system submit more than one project application if it has several construction projects going on in the same building?
A: No. Project applications must be limited to one project per building, and no building can be the subject of more than one application per year. However, a project application may include seemingly unrelated components within a single building as long as the project is within the construction aid program guidelines.
Q: If a library or library system has a main library and several branches, can the library or library system apply for construction aid for more than one of the buildings in the same year?
A: Yes. If a library or library system has multiple buildings (a main building and one or more branches), the library or library system may apply for construction aid for each building. One project application is required for each building.
Q: If the library system headquarters building is also the system’s central library, may the system apply as both a system and a member library?
A: Yes. If the library system headquarters building also serves as the system’s central library, the system can use funds from both the sixty percent reserved for member libraries and the forty percent of money available for use by the library system. (See “How is construction aid funding distributed throughout the state?” below.)
Q: What is the application deadline?
A: The deadline for submission of applications from the systems to the State Library is 5:00 p.m., Wednesday, October 3, 2018. However, each public library system will set its own deadlines for member libraries to submit applications to allow sufficient time for system review and system board approval. Please contact your public library system to find out its due date.
Q: How does the project approval process work?
A: If the applicant is a library, the application for State Aid for Library Construction must first be submitted online to the public library system for review and evaluation. The public library system board reviews and evaluates each library’s application and then submits the approved applications, along with a funding recommendation to the New York State Library. If the applicant is a library system, the system will submit the system application directly to the State Library along with the member library applications. The system application must describe how the project to enhance the system headquarters building will improve system services to member libraries and users. The library system board must “rank the applications from its system area in order of its recommendations, giving particular attention to the service needs of any communities which are isolated, economically disadvantaged or located beyond the reasonable service capabilities of other libraries which are members of such library system.” The submission process for both the library to the library system and the library system to the State Library is an online process.
The State Library will review project applications and submit approved project applications and supporting documents to the Dormitory Authority of the State of New York (DASNY) for review and final approval.
Dormitory Authority bond proceeds will be used to reimburse the State of New York for allocations made under this program. Therefore, the Dormitory Authority will need to review each application for statutory and tax law compliance. In addition, the Dormitory Authority will undertake the SEQRA review, unless another lead agency has already conducted an appropriate review. Once the Dormitory Authority and the State Library have approved the application, paperwork will be processed for the initial aid payment.
Program Specifications
Q: If a construction project is already completed, can the library/library system apply for funding retroactively?
A: No. Projects cannot be completed prior to the date of the application**. Applications for completed projects will not be approved. (** The date of application means the deadline date for receipt of applications by the library system.)
Q: If a project has already begun but is not completed at the time of application, can the library/library system apply for funding for the cost of all work already completed prior to the filing of the application?
A: No. Aid can be provided only “on approved expenses incurred during the period commencing July first and ending June thirtieth” of the funding year “for up to three years, or until the project is completed, whichever occurs first.” Any costs incurred before July 1, 2018, are not eligible for direct construction aid for the 2018-2021 funding cycle. However, funds expended on the project between January 1 – June 30, 2018, can be considered match funds and may be included as part of the total project cost.
Q: Is there a minimum/maximum allocation amount?
A: The minimum allocation is $2,500. There is no maximum, but the amounts of the aid will depend on the number of project applications received and the total funding available.
Q: What kinds of projects are eligible for funding under State Aid for Library Construction?
A: Costs eligible for approval include construction or acquisition of a library building, renovation or rehabilitation of a library building, or renovation or rehabilitation of a building leased for library purposes. The purchase and installation of equipment and furnishings are eligible costs within the context of a construction project application for a new building, building addition or substantially renovated/rehabilitated space. Assistive listening devices and systems are eligible expenses. The purchase, installation or replacement of a library's broadband infrastructure is eligible. Other eligible costs include site acquisition (purchase of vacant land or an existing building to be used for library purposes), site grading of owned property in conjunction with a building project, and supervision/management of the construction, renovation, or rehabilitation. The purchase and installation of one or more generators is also an eligible expense. The program gives priority to projects that increase energy conservation, provide accommodation for computer equipment and new technologies and brings libraries into compliance with the Americans with Disabilities Act. Libraries and library systems are encouraged to support “green” projects that may result in buildings eligible for LEEDS certification. Priority is also given to projects that will extend library services to people residing in geographically isolated and economically disadvantaged communities.
Q: Can a library buy computers and equipment and incorporate new technologies as part of a construction project?
A: Yes, a library or system may use the construction funds to purchase computers and equipment that will upgrade the library or system’s technology capabilities—e.g., automated systems that permit library users to check out materials themselves, public access computers for a newly constructed computer lab. The purchase of new technologies must be within the context of a construction project for a new building, building addition, or a substantial renovation/rehabilitation project. Requests for new computers that are not intimately connected to a construction/rehabilitation project are not eligible for funding from this program. The purchase, installation or replacement of broadband infrastructure is eligible as a stand-alone project.
Q: Can State Aid for Library Construction funds be used for Broadband infrastructure projects?
A: Yes, the purchase, installation or replacement of broadband infrastructure is eligible as a stand-alone project. The purchase of initial necessary equipment or the upgrade of existing equipment, such as servers, routers and wireless hubs are also eligible expenses as part of a broadband project.
Broadband infrastructure projects involving fiber buildout that are eligible for State Aid for Library Construction funds should meet the following criteria:
- Such projects should involve the creation of or the use of a “last mile” fiber buildout to the library(ies) or library system(s) building(s);
- Such projects should either utilize or create fiber connections that have the capacity to deliver internet services at a connectivity rate of at least 100Mbps for libraries and library systems that serve fewer than 50,000 people and at least 1Gbps for libraries and library systems that serve 50,000 people or more.
Broadband Wireless Projects
- Broadband wireless projects eligible for State Aid for Library Construction funds should create wireless connections that have the capacity to deliver Internet services at a connectivity rate of at least 100Mbps for libraries and library systems that serve fewer than 50,000 people and at least 1Gbps for libraries and library systems that serve 50,000 people or more.
- Such projects could involve hardware purchases, including required servers, for initial installations and for existing installations that have been upgraded to the minimum required connectivity standards indicated in Number #1.
Q: If a library participates in a coordinated project with a Library System to provide broadband services to its own building and additional library buildings is the library allowed to apply for an individual project for their building?
A: Yes. Participation in a coordinated project with a Library System to provide broadband services to several library buildings does not preclude a library from submitting an individual application.
Q: Will a project that consists of building maintenance be eligible for funding under State Aid for Library Construction?
A: No. Commissioner Regulations specifically exclude “routine maintenance” from eligible funding categories. Projects with emphasis on repair and/or building upkeep and tasks that need to be done on an annual basis are generally considered to be routine maintenance. This includes tasks that involve keeping any sort of mechanical, plumbing or electrical device in working order (preventive maintenance).
Expensive projects with a large scope that are not done every year, such as carpet replacement for large areas of the building and repointing bricks are not considered routine maintenance. Brick repointing as a stand-alone project is eligible for funding, as it is a safety issue. However, carpet replacement as a stand-alone activity does not qualify as a construction project. The carpet replacement must be a component of a construction / renovation project, such as sub flooring replacement, a renovation project that creates new space, the creation of a building addition or a completely new building.
Q: Are project management costs eligible for funding?
A: Yes, project management costs of the construction, renovation, rehabilitation or broadband library services infrastructure project, including such costs as project manager and clerk of the works, are eligible for funding.
Q: Are architectural and engineering plans eligible for funding?
A: Yes, architectural and engineering plans for locally approved new or ongoing projects, provided they are submitted in the same application as the relevant project, are eligible for funding.
Q: In addition to routine maintenance, are there any other costs ineligible for funding under State Aid for Library Construction?
A: Yes. Other costs ineligible for funding include, but are not limited to, speculative architectural and engineering plans, building consultant feasibility studies, interest or carrying charges on bonds financing the project, purchase of books and other library materials, and landscaping. Library signage (with or without lighting) is not considered landscaping and is an eligible expense.
Q: What are the matching fund requirements?
A: State aid for library construction can be provided for “up to seventy-five percent of the total project approved costs for buildings of public libraries that are located in an economically disadvantaged community,” as determined by the library’s library system. Public libraries that are located in communities that are not identified by the library system as economically disadvantaged communities are eligible for a maximum of fifty percent of the total project approved costs.
Before applications are approved, applicants must provide evidence of the availability of funds to pay for the cost of the project, minus the amount allocated through State Aid for Library Construction. Verification must be in the form of bank or bond certification, an official document(s) signed by a financial authority connected with the applying institution, and/or such other evidentiary documents as necessary. Note: Library applicants do not receive the final 10% of the aid until the project is completed and closed. Applicants need to make sure sufficient funds are available to complete projects.
Q: Can State and Municipal Facilities Program (SAMS) money be used as match funds for a construction project?
A: No. SAMS money cannot be used as matching funds for your project. Chapter Law 54 of 2014 states: “No funds from this appropriation may be used as a required match or be considered a local share to other state programs or to leverage state aid or grants including but not limited to the apportionment of aid under the education law.”
Additional project costs that are not paid for by the aid or required local match funds can be paid for by SAMS funds.Q: What documents are required if the project involves bonding?
A: If the project for which a library has submitted an application is or will be funded in whole or in part through the issuance of tax-exempt bonds, bond anticipation notes, revenue anticipation notes, or some similar form of obligation, the application must include the applicable authorizing resolutions adopted by the library or issuing party authorizing the bond issuance, a detailed breakdown of the expected or actual sources and uses of bond proceeds, equity or other funding sources for the project, a copy of the final official statement relating to the applicable issuance if available and a current cost estimate of the entire project including:
- Provide a detailed breakdown of all project costs regardless of whether or not they will be funded with allocations. Indicate which costs are related to aid funds.
- Provide the total dollar amount that is being bonded for the project.
- If BANS are issued, a letter is required asserting that at the time BANS are converted to Bonds, the Bond issued for the project will be in an amount not to exceed the total cost of the project minus the allocation.
Keep in mind that since State Aid for Library Construction projects are funded with tax exempt bonds, the only portion of the project that can be funded with bonds is the total cost of the project minus the amount allocated that is being requested.
Q: How soon after an allocation is made must a library or library system begin construction?
A: The project, if not already started at the time of application, must begin within 180 days after approval. (**The date of approval is the date on the official electronic approval letter from the NYSL/Division of Library Development to applicants informing them that their application for funding has been approved.) Applicants must indicate assurance on the application that the project will begin within 180 days of approval. The 180-day certification must be completed and submitted to the NYSL/Division of Library Development when requested.
Q: How much time does a library/library system have to finish the construction project?
A: There is a three-year allowance for project completion under State Aid for Library Construction. For applications submitted for FY 2018, projects must be completed by June 30, 2021. If a project is not completed by the end of the second year, June 30, 2020, the library or library system must file a progress report with the State Library for an extension to be granted for the third year. There is no allowance for further extensions beyond the three years. If a project is not completed by June 30, 2021, the State Library may request the return of any unexpended state money allocated for the project.
Q: Will an estimate provided by an architectural, engineering firm, or construction consulting firm be adequate for cost estimation?
A: No. A project cost estimate that is a reliable assessment of true project cost must accompany the application. Such estimate must be in the form of a quote document from a contractor(s) to assure that the full cost of the project can be reliably assessed. If the construction project is multifaceted and more than one contractor will be involved, e.g., an electrician, plumber and carpenter, a quote document from each contractor is required. Cost estimates from architects, engineering firms, or construction consulting firms are not acceptable.
A library does not have to have entered into final agreements with a contractor(s) at the time of application. However, allowing for reasonable increases in the cost of construction from the time the application is submitted, great care should be taken to assure that the cost estimates reflect anticipated true cost to ensure that sufficient funds are available to pay for the cost of the project, minus the allocation amount.
Q: What is the payment schedule for aid?
A: Fifty percent of the allocation is payable after January 1, 2019, pending final approval of the application if not rendered prior to that date. Forty percent of the allocation is payable after April 1 of the year following the release of applications (for 2018 applications, that will be April 1, 2019). Typically, libraries will receive their first payments in the spring. The remaining ten percent is payable upon project completion and filing of an approved FS-10-F, post-project photographs, and a Certificate of Occupancy if applicable to the project.
Q: Does the library receiving construction aid have to file additional paperwork to get the second payment of 40%?
A: No. The State Library will take action to trigger that payment to each of the libraries receiving aid under the construction program.
Q: What if there is a change in a project activity?
A. No project activity changes can be made during the program activity period without the approval of the State Library.
Formula Aid Breakdown
Q: How is construction aid funding distributed throughout the state?
A: Sixty percent of the $34 million ($20.4 million) is available solely for member library projects. That sixty percent is based on population served. The amount received by each system for its member libraries is no greater than the ratio of the population served by the system to the population of the state as a whole. Forty percent of the $34 million ($13.6 million) is available for use by the library system and/or its member libraries and is divided equally among the 23 public library systems. Each library system receives the same amount.
Q: What happens to construction aid funds that are not allocated to libraries or systems within a particular library system as determined by the formula distribution?
A: If a library system is unable to use all of its formula allocation, the State Library will reallocate the unused portion of the system’s funds to other approved construction projects in other library systems.
Building Code and Other Requirements
Q: Are libraries required to comply with public building codes relating to the Americans with Disabilities Act (ADA)?
A: Yes. New and renovated public library and library system buildings are required to be in compliance with all current ADA regulations, which include addressing specific requirements such as assistive listening devices and systems. Priority is given to construction projects that provide improved access to and use of building services by persons with physically handicapping conditions.
Q: Are libraries required to pay prevailing wages for projects funded through State Aid for Library Construction?
A: Public libraries, as described in Section 253(2) of NYS Education Law, are subject to the prevailing wage law. Free Association libraries are usually not subject to such law, unless they are involved in construction contracts that take place on municipal property or involve municipal use. In the case of Free Association Libraries, prudence would dictate that such libraries contact the Department of Labor and request a determination as to the applicability of the prevailing wage law in the particular circumstances then present. Projects subject to the prevailing wage law require the payment of certain minimum wages for all laborers, workers and mechanics, and it is vital that such information be provided to any party bidding on such a project.
Q: What is SHPO? What libraries must meet SHPO requirements?
A: SHPO, New York’s State Historic Preservation Office, is part of the New York State Office of Parks, Recreation and Historic Preservation. The mission of SHPO is to help communities identify, evaluate, preserve, and revitalize their historic, archaeological, and cultural resources.
If your library building is 50 years old or older and/or the project involves ground disturbance and/or demolition, please read the following documents to determine if your project requires a SHPO approval:
- Formal Agreement with the State Education Department (.PDF format only
[619k])
If appropriate, an approval letter from SHPO must be attached to the library’s construction application as a signed PDF.
In the event a building is determined by SHPO to be of historical significance, the SHPO approval letter must specify the precise changes to the building that are being approved. Any project components not specifically approved in writing will not be considered for funding. In the event a building is determined by SHPO to lack historical significance, a letter to that effect from SHPO must accompany the application. Such letter may be used in subsequent years to comply with construction application requirements.
For more information about SHPO requirements, please call 518-237-8643. You will be directed to the regional office in the area where the library building is located.Q: What is the State Education Department's Office of Facilities Planning? What libraries must meet Office of Facilities Planning requirements?
A: The State Education Department’s Office of Facilities Planning is charged with enforcing the New York State Uniform Fire Prevention and Building Code with respect to buildings, premises, and equipment as they relate to school districts and Boards of Cooperative Educational Services (BOCES). If a public library is housed in a building owned or operated by a school district or BOCES and is applying for construction aid for a project costing $10,000 or more, the library must submit plans and specifications to the Office of Facilities Planning for approval before the application will be considered for funding by the State Library.
NOTE: The designator “school district public library” does not necessarily indicate ownership of a library building by the school district; rather, it refers only to the boundaries of population served by the library. OFP approval is required only if the building is OWNED by a school district or BOCES, regardless of the library’s service area.
For more information about SED Office of Facility Planning requirements, please call 518-474-3906. You will be directed to the appropriate Project Manager for the school district in which the library building is located.
Q: What is the State Environmental Quality Review Act (SEQRA)? What libraries must meet SEQRA requirements?
A. The State Environmental Quality Review Act requires certain entities, including state agencies, public benefit corporations and certain libraries, to evaluate the potential environmental consequences of certain activities and to minimize adverse impacts. Accordingly, a SEQRA review must be undertaken in connection with projects funded under State Aid for Library Construction.
All applicants must complete the Short Environmental Assessment Forms (SEAF) as part of the application process. A map showing the location of the project must be attached to SEAF Part 1.
In most cases, the SEAF will suffice to commence the SEQRA process. In certain cases, however, the applicant may need to complete a long form EAF.
More information on Environmental Assessment Forms.
Q: Does a library/library system need to provide a copy of the “Certificate of Occupancy” if applicable?
A. Yes. If the project requires that a local “Certificate of Occupancy” be obtained at the completion of the project, a copy of the certificate must be scanned and attached as part of the Final Project Completion activities. Note: the library cannot receive final payment until all of the required Final Project Completion activities are complete.
Examples of when a “Certificate of Occupancy” is typically required include: New Building Construction; Construction or renovation that significantly changes the current or intended use of library space. For example, a space that is currently used for offices or storage and is converted to public use space would possibly require a certificate of occupancy. Be sure to consult and follow local government laws as they apply to certificates of occupancy to ensure compliance.